Proudly serving all of Florida with offices in Tampa, Orlando, and Fort Myers

  • Helicon
  • 9
  • Underpinning and Chemical Grout: Multi-Use Commercial Building, Tampa, FL

The Plaza at Harbour Island

Tampa, FL

Client: Plaza Harbor Island Condo Assoc.

Market: Commercial

Solution: Foundation Repair

Services: Chemical Grout, Underpinning

Foundation Repair for a Multi-Use Complex Improvement of the clayey sands and silty soils Micropiles installed to a 45-50 ft depth range

The Project

The project is a multi-use complex, including retail space and multi-level condominiums/apartments. The Geotechnical Engineer of Record recommended a foundation repair of underpinning micropiles and chemical grout injections to solve settlement problems.

The Challenge

  • Bay bottom sediments of very loose silty to clayey sands and clays with differing silt, sand, and shell content.
  • The surface of the limestone formation was encountered between 33 feet and 44 feet.

The Solution

Helicon worked alongside the geotechnical design team to develop a foundation repair program designed to meet the building code load criteria. Micropiles were installed to a depth range of 45-50 feet below existing grade. The support brackets for the micropiles allow not only prevention of further settlement of foundation elements but also can be utilized to provide some uplift of foundation elements. Chemical grout injections were completed to give additional support to the foundation. Efficient planning & coordination was key to overcoming the challenges & limitations. Helicon collaborated with the Geotechnical Engineer of Record throughout the work and confirmed all recommended criteria were followed.