Proudly serving all of Florida with offices in Tampa, Orlando, and Fort Myers

Compaction Grout: Suncoast Parkway Extension, Spring Hill, FL

i 3 Table of Contents

Cracked Foundation Wall Repair Tips for Lasting Home Stability

Noticed a crack running along your foundation wall? It might seem like just a surface issue, but it could be a sign of something more serious. Foundation cracks, if left untreated, can impact your home’s structural integrity, safety, and long-term value. These cracks...

Signs of structural foundation failure to watch for in your home

Your home’s foundation is the backbone that holds everything together. When it starts to fail, the signs can be subtle—or sometimes glaringly obvious. Noticing these warning signals early can save you from costly repairs and keep your family safe. Have you seen cracks...

New Pool Foundation Support Tips for a Strong and Lasting Build

Building a new pool is an exciting project, but have you thought about what’s beneath the surface? Your pool’s foundation plays a crucial role in ensuring that your backyard oasis stays beautiful, safe, and durable for years to come. In places like Florida, where soil...

Residential Ground Support Solutions for Safe and Stable Homes

Have you noticed cracks in your walls, uneven floors, or doors that don’t close right? These could be signs your home’s foundation or soil is struggling. Left unchecked, weak soil and foundation issues can cause serious damage, leading to costly repairs and unsafe...

Contact us anytime!

[cs_content][cs_element_section _id=”1″ ][cs_element_row _id=”2″ ][cs_element_column _id=”3″ ][cs_element_headline _id=”4″ ][/cs_element_column][/cs_element_row][/cs_element_section][cs_element_section _id=”5″ ][cs_element_row _id=”6″ ][cs_element_column _id=”7″ ][cs_element_video _id=”8″ ][cs_element_gap _id=”9″ ][/cs_element_column][cs_element_column _id=”10″ ][cs_element_headline _id=”11″ ][cs_element_gap _id=”12″ ][cs_element_text _id=”13″ ][cs_element_gap _id=”14″ ][cs_element_headline _id=”15″ ][cs_element_headline _id=”16″ ][cs_element_headline _id=”17″ ][cs_element_gap _id=”18″ ][cs_element_button _id=”19″ ][cs_element_social _id=”20″ ][cs_element_social _id=”21″ ][cs_element_social _id=”22″ ][cs_element_social _id=”23″ ][/cs_element_column][/cs_element_row][/cs_element_section][cs_element_section _id=”24″ ][cs_element_layout_row _id=”25″ ][cs_element_layout_column _id=”26″ ][cs_element_text _id=”27″ ][cs_element_text _id=”28″ ][/cs_element_layout_column][/cs_element_layout_row][/cs_element_section][cs_element_section _id=”29″ ][cs_element_layout_row _id=”30″ ][cs_element_layout_column _id=”31″ ][cs_element_text _id=”32″ ][cs_element_text _id=”33″ ][/cs_element_layout_column][/cs_element_layout_row][/cs_element_section][cs_element_section _id=”34″ ][cs_element_layout_row _id=”35″ ][cs_element_layout_column _id=”36″ ][cs_element_text _id=”37″ ][cs_element_text _id=”38″ ][/cs_element_layout_column][/cs_element_layout_row][/cs_element_section][cs_element_section _id=”39″ ][cs_element_row _id=”40″ ][cs_element_column _id=”41″ ][cs_element_image _id=”42″ ][cs_element_image _id=”43″ ][cs_element_gap _id=”44″ ][/cs_element_column][cs_element_column _id=”45″ ][cs_element_image _id=”46″ ][cs_element_image _id=”47″ ][/cs_element_column][/cs_element_row][/cs_element_section][/cs_content][cs_content_seo]Suncoast Parkway Project

Spring Hill, FL

CLIENT: Lane Construction
ENGINEER: Jacobs Engineering
MARKET: Infrastructure
SOLUTION: Ground Improvement
SERVICE: Compaction Grout

Ground improvement for a highway expansion

Compaction Grout mixture of 250 psi

Slump of 3-5 inches and pressure up to 600 psi

Project PDF

Project

Construction started on Phase 1 from US 98 to SR 44 in February 2018. The 13-mile stretch is expected to be completed by 2022. The funding for this project is based on Turnpike tolls and concession revenues. This highway expansion is the largest expansion since the mid-1950’s. The current Suncoast Parkway stretches just under 60 miles from Hillsborough County to Citrus County. With this ambitious new plan, the road would extend another 150 miles to Georgia. The economic impact to this region could be a boom for local businesses and the local construction industry.

Challenge

The challenges encountered during compaction grout installation were minimal:• Critical path construction schedule

Solution

Helicon worked alongside the general contractor & the engineer teams, to develop a cost-conscious compaction grout project submittal. The Compaction Grout Project was designed to stabilize and improve subsurface conditions by means of compaction grouting within Pond 2-5G in the vicinity of Ramp A between Stations 1268+30 and 1268+80 (in the vicinity of Boring AN-6). Compaction grouting occurred prior to the retention pond construction and excavation. Efficient planning & coordination was key to overcoming the challenges & limitations.The purpose of the compaction grouting was to compact, plug, and seal potential avenues for further migration of the overlying soils, thereby minimizing the possibility of future subsidence and distress to the proposed improvements. The compaction grout work was successfully completed on-time and within budget. Image Image Image Image [/cs_content_seo]